Site visit & soil
We walk the plot, check access, levels, the water table and neighbouring structures, and order a bearing capacity test where the foundation calls for one.

Process
Nothing on this list can be skipped or resequenced. Each stage ends in a document you keep, which is what makes the next stage checkable.
We walk the plot, check access, levels, the water table and neighbouring structures, and order a bearing capacity test where the foundation calls for one.
Plans, elevations and the structural set, coordinated with Vaastu requirements where the family follows them, and revised until you sign off.
A line-by-line bill of quantities against the approved drawings, a fixed specification, a payment schedule tied to stages, and a written agreement.
Excavation, footing, column starters, plinth beam and backfill. Concrete cubes cast and sent for seven and twenty-eight day testing.
Columns, beams and slabs floor by floor, then masonry and plaster. Photographs of reinforcement go to you before every pour, not after.
Electrical, plumbing, flooring, joinery and painting, then a joint snag list, clearance of every item on it, and handover with the as-built set and warranties.
Specification
The grade of every material we build with, in writing, before you sign. If another quote is cheaper, this table is where the difference will be.
| Element | Specification | Standard |
|---|---|---|
| Foundation | Isolated / raft footing to soil report | IS 1904 |
| Concrete | M20 for footings, columns, beams and slabs | IS 456:2000 |
| Reinforcement | Fe 500D or FE 550D TMT, ISI marked | IS 1786 |
| Cement | OPC 53 grade structure · PPC masonry | IS 269 / IS 1489 |
| Masonry | AAC blocks 200 mm external · 100 mm internal | IS 2185 |
| Plaster | External 15 mm double coat · internal 12 mm | 1:5 / 1:6 CM |
| Waterproofing | Crystalline to sunk slabs, terrace & basement | 10 yr warranty |
| Electrical | FR copper wiring in concealed PVC conduit | IS 694 |
| Plumbing | CPVC supply · PVC drainage, concealed | IS 15778 |
| Doors | Teak frame, main door teak, internals flush | — |
| Windows | UPVC sliding with mosquito mesh & grill | — |
| Flooring | 800×800 vitrified · anti-skid in wet areas | — |
| Painting | Interior emulsion · exterior weather coat | 2 coats + primer |
| Testing | Concrete cubes at 7 and 28 days, third party | IS 516 |

Free site visit & estimate
Take this table to whoever else has quoted you and ask them to fill in the same rows. That comparison is worth more than a headline rate.