What will it cost to build?
Most builders will not answer this until you are sitting in their office. Here is the arithmetic we use, with our rates in it, so you can do the sum yourself before you call anyone.
What is included in Standard
Everything below is in the rate shown. Structure is identical in all three specifications; they differ in finishes and joinery.
Structure
- Excavation, PCC bed, isolated or raft footings as per structural design
- RCC columns, beams, slabs and staircase in M20 concrete
- Fe 500D or FE 550D TMT steel from a primary-producer brand, with mill test certificates
- Cube tests for every pour and a photo record of reinforcement before casting
Masonry & plaster
- Solid or AAC block masonry, 9 in external and 4.5 in internal walls
- 12 mm internal and 20 mm external cement plaster, ceilings finished smooth
- Minimal exterior elevation: plain plastered facade with simple bands and sill and lintel projections
- Plastering curing for a minimum of 7 days
Flooring & tiling
- Vitrified tiles 800×800 in living, dining and bedrooms
- Anti-skid tiles in bathrooms and balcony, wall tiles to 7 ft in bathrooms and 4 ft above kitchen platform
- Granite kitchen platform with stainless steel sink
- Tile skirting throughout
Doors & windows
- Main door: teak frame and teak-veneered or panelled shutter, with a branded lock set
- Internal doors: flush shutters on hardwood or sal frames
- Windows: UPVC sliding or casement with glass, grills and mosquito mesh
- Bathroom doors: waterproof PVC or FRP
Electrical
- Concealed fire-retardant copper wiring in conduits
- Modular switches and sockets, MCB distribution board with ELCB
- Basic light, fan and AC points in every room, TV and internet conduits in living room
- Fixtures such as light fittings and fans are not included
- Geyser points in all bathrooms, and a separate circuit for each AC
Plumbing & sanitary
- CPVC or UPVC concealed water supply, PVC drainage
- Branded sanitary ware, wall-hung or floor-mounted EWC and washbasin per bathroom
- Branded CP fittings, with shower, health faucet and 2 taps per bathroom
- Overhead tank and sump to standard capacity
Painting
- Putty, primer and 2 coats of premium acrylic emulsion inside
- Exterior weather-proof emulsion, 2 coats over primer
- Enamel on grills and railings
Waterproofing & finishing
- Terrace, bathrooms and sunk slabs waterproofed
- MS railings for staircase and balcony
- Final cleaning before handover
Where the money goes
Percentages of construction cost, against the midpoint of the range above.
| Stage | Share | Amount |
|---|---|---|
| Excavation & foundationEarthwork, footings, plinth beam, backfill | 11% | ₹5,61,924 |
| RCC structureColumns, beams, slabs, staircase. Steel and concrete | 27% | ₹13,79,268 |
| Masonry & plasterBlock work, internal and external plaster, minimal exterior elevation | 11% | ₹5,61,924 |
| Flooring & tilingLiving areas, bedrooms, wet areas, skirting | 9% | ₹4,59,756 |
| Doors & windowsFrames, shutters, glazing, grills, hardware | 9% | ₹4,59,756 |
| ElectricalConduits, wiring, boards, points, fixtures | 7% | ₹3,57,588 |
| Plumbing & sanitarySupply, drainage, fittings, overhead and sump tanks | 7% | ₹3,57,588 |
| PaintingPutty, primer, interior emulsion, exterior weather coat | 5% | ₹2,55,420 |
| Waterproofing & miscTerrace, sunk slabs, railings, site clearance | 8% | ₹4,08,672 |
| Supervision & overheadsSite engineer, scaffolding, machinery, testing | 6% | ₹3,06,504 |
When you would pay
Against work finished and measured, never against a calendar date.
| On signing the agreement | 20% | ₹10,21,680 |
|---|---|---|
| Foundation and plinth complete | 10% | ₹5,10,840 |
| Ground floor slab cast | 15% | ₹7,66,260 |
| Upper slabs cast | 15% | ₹7,66,260 |
| Masonry and plaster complete | 15% | ₹7,66,260 |
| Flooring, doors and windows complete | 12% | ₹6,13,008 |
| Electrical, plumbing and painting complete | 8% | ₹4,08,672 |
| Handover after snag clearance | 5% | ₹2,55,420 |
Not included in this figure
- Land cost, registration and stamp duty
- Government approval fees, development charges and deposits
- Compound wall, gate, landscaping, external paving and elevation work beyond the minimal plain elevation
- Borewell, sump beyond standard capacity, and water connection
- Lift, solar, air conditioning and home automation
- Modular kitchen, wardrobes and loose furniture
- GST, charged at the applicable rate on the contract value
This is an indicative range from published rates, not a quotation. A real number needs the plot, the soil and your drawings. The first visit and the written estimate cost nothing.
Rates are reviewed periodically and apply to Andhra Pradesh & Karnataka. Steel and cement move with the market, so a rate quoted today is held for the period stated in your agreement and not indefinitely.