Straight answers, including where the honest answer is that it depends. The first two are the questions we are asked before anything else.
What does construction cost per square foot in Tirupati and Bengaluru?
It depends almost entirely on specification, not on the builder. A standard residential turnkey package using M20 concrete, Fe 500D or FE 550D steel, AAC blocks and vitrified flooring generally falls in a band we will quote you in writing (Bengaluru runs higher than Andhra Pradesh, mainly on labour) after seeing the plot and your drawings. Our published rates and a stage-by-stage breakdown are on the cost page, so you can do the sum yourself before calling anyone. We also publish the full material specification, so you can compare any two quotes line by line instead of comparing headline rates.
How long does a G+1 house take to build?
For a typical 3,000 to 4,000 sq.ft duplex on a clear plot with approvals in hand, ten to twelve months from foundation to handover is realistic. Monsoon, approval delays and changes made after the drawings are signed are the three things that usually extend it.
Do you work on a per square foot rate or item rate?
Both. A per square foot rate is simpler for a straightforward house with a fixed specification. Item rate suits projects where the scope is likely to move, because every change is measured and priced against a rate that was agreed at the start. We will tell you which one fits your project.
Will you follow Vaastu requirements?
Yes. Vaastu inputs are taken at the drawing stage, before the structural design is fixed, because moving an entrance or a kitchen after the framing layout is settled is expensive. Bring your consultant's notes to the first meeting.
Can you handle building permission and approvals?
Yes. We prepare the permission drawing set, submit it and follow it up with the local authority, and prepare occupancy documentation at the end. Statutory fees are paid by the owner at cost.
What happens if something is defective after handover?
Any workmanship defect reported within twelve months of handover is rectified at our cost. That defect liability period is written into the agreement rather than being a verbal assurance.